MCSC completed major repair and maintenance activities in GPIC Ammonia and Methanol plants during the Shutdown in November 2007. Major jobs executed during the 18 days T&I are given below:
Methanol Plant:
Renewal of Process Gas Cooler (E 1201). Total weight - 50 Tones.
Renewal of EB 1202-2 Convection Coil (EB - 1202-2). Total weight - 45 Tones).
Renewal of Reformer Tubes (B 1201).
Heavy schedule butt welds were examined using advance NDT method of ToFD Ultrasonic Testing.
Ammonia Plant:
Renewal of Secondary Reformer (R 0301). Total weight - 310 Tones.